A weakly drafted contract meant the Driver and Vehicle Agency (DVA) took years to get rid of a company which was failing to deliver an upgrade of its vehicle testing centres, a spending watchdog has found.
The NI Audit Office (NIAO) investigated the botched deal which wasted £5m and has contributed to long delays in improving the MOT centres.
It found that the company involved had fallen six weeks behind schedule within just six months of winning the contract in 2019.
After a protracted legal process it was eventually paid £1.5m to go away in 2025, described as "a significant fruitless expenditure".
The NIAO does not name the company but the BBC has previously reported that it is Worldwide Environmental Products Inc. (WEP Inc).
The Auditor General Dorinnia Carville said: "This report evidences a missed opportunity to improve much needed services, as well as a significant waste of public money."
Aside from the money paid to terminate the contract a further £3.6m was spent on the project.
"Once serious problems emerged, weaknesses in the contractual arrangements made it more difficult to bring the contract to a timely conclusion," Carville added.

By February 2022 the DVA had issued two formal warnings to WEP Inc for poor performance and moved to terminate the contract.
However the company won a High Court challenge when a judge ruled that the contract did not specify clear dates for the implementation of key systems.
DVA attempted to persevere with the deal before it was eventually terminated ahead of a second court case in April 2025.
The report also identifies weaknesses in the procurement process which led to WEP Inc winning the contract in the first place.
Its successful tender was priced at £10.8m, 53% lower than the only other compliant bid and 40% below the DVA's business case estimate.
DVA did follow the correct procurement processes and further checks were undertaken, but these did not provide sufficient assurance that the proposed solution could be delivered at the price quoted.
Lessons identified from project
The report also highlights limited scrutiny of the proposed IT solution, which subsequently became a major source of disagreement between the DVA and the company.
Carville said the DVA and Stormont's Central Procurement Directorate have identified lessons from the project, and there is evidence that these have been acted upon to improve subsequent procurement exercises.
Carville added: "It is vital that learning is shared beyond these two organisations, particularly as today's findings echo those in previous reports by the NIAO on the delivery of major IT projects."
A replacement contract for the testing centres was awarded in March this year at a value of £46m, with completion expected in mid-2029.
The report notes that direct comparison with the original £10.8m bid is difficult because of changes in the project scope, implementation assumptions and contract lifespan.
A spokesperson for the Department for Infrastructure said: "The Department welcomes the publication of the NIAO Report and is considering the findings. No further comment will be made until the Assembly process is complete."